logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울남부지방법원 2018.11.08 2018가단219387
임금
Text

1. The defendant,

A. As from November 15, 2017, the Plaintiff A andO KRW 4,420,00 for each of them:

B. Plaintiffs B, D, E, F, G, K.

Reasons

1. Comprehensively taking account of the overall purport of the pleadings as to the statements in Gap evidence Nos. 1 through 3 and Eul evidence Nos. 1, the defendant was awarded a subcontract for reinforced concrete construction works from U.S. and limited liability companies V to KRW 2,695,00,000 among the new construction works of Wmiddle School Teachers from U.S. on February 6, 2017. The plaintiffs provided labor to the above construction site from May 2017 to October 2017. The defendant prepared a written confirmation that the plaintiffs promised to pay the unpaid wages to November 15, 2017, and the fact that the wages the plaintiffs did not receive are the amount indicated in the text of the order.

Thus, the defendant is obligated to pay to the plaintiffs the amount of money stated in the order and damages for delay calculated at the rate of 20% per annum as provided by the Labor Standards Act from November 15, 2017 to the date following the 14th day after the payment date (However, from November 14, 2017 to the date of full payment).

2. As to this, the Defendant asserted that since the Defendant re-subcontracted construction to X and paid all the contract amount to X, it is impossible to comply with the Plaintiffs’ request, but the Defendant’s assertion alone cannot reverse the above judgment.

3. Therefore, the plaintiffs' claims of this case are accepted on the grounds of all.

arrow