Text
1. The Defendant’s KRW 40,000,000 as well as the annual rate of KRW 6% from November 14, 2017 to August 28, 2018, and the following day.
Reasons
1. Facts of recognition;
A. On September 28, 2016, the Plaintiff (CGeneral Certified architect Office Operation) and the Defendant concluded a supervision agreement between the Defendant and the Plaintiff regarding “E Corporation” (hereinafter “E Corporation”) to be performed by the Defendant on the land, etc. of Hanam-gun, Hanam-gun, etc. (hereinafter “instant construction”) with respect to supervision costs of KRW 240,000,000 (excluding value-added tax) and the date of the commencement of the supervision period
(hereinafter “instant supervision agreement”). The instant supervision agreement includes the following:
Article 2 (Period of Work) (1) The period from the commencement to the completion date of construction supervision shall be the period.
(2) When the construction work is temporarily suspended due to the defendant's circumstances, the suspension of construction work becomes effective upon the defendant's notice of the suspension of construction or the plaintiff's written confirmation to the defendant, and the plaintiff may not claim supervision
Article 3 (Methods of Calculation and Payment of Construction Supervision Expenses) (2) Remuneration for the construction supervision affairs may be paid in lump sum or in installments, and the construction supervision expenses incurred due to the extension of construction period during the performance of duties shall be settled in consideration of the amount of the supervision contract and the extended period
(3) In the case of installment payments of remuneration, the time of payment and the amount of payment shall, in principle, be as follows, and may be adjusted through consultation between the defendant and the plaintiff:
Article 7 (Commencement of Work) of the 12,000,000,000 Value-Added Tax for the first and second progress payment of 12,000,000 on December 30, 2016 at the time of receipt of separate commencement of the 12,000,000 Value-Added Tax for the second and second progress payment of 24,000,000 on March 30, 2017 (Time of Commencement of Work) ① The Defendant shall notify the Plaintiff of the date of commencement three days prior to the commencement of the work, and the Plaintiff shall commence construction supervision from the commencement date of the work.
Article 22 (Payment of Remuneration when Suspension of Construction Supervision Affairs) (1) Where all or part of the construction supervision affairs has been interrupted due to the defendant's fault, the defendant shall pay the remuneration until the suspension is made for the construction supervision affairs already performed by the plaintiff.
B. The head of the Haban Gun shall be on January 2016.