(영문) 서울고등법원 2017.09.01 2015나10402
공사대금등
Text

1. Part of the claim for construction cost, part of the claim for additional construction cost, official tools and expendable materials in the judgment of the first instance.

Reasons

1. Scope of trial of this court after the progress of lawsuit and remand;

A. The plaintiff in the main claim is seeking as the main lawsuit the following items and details related to the mechanical pipeline construction works (hereinafter "the instant mechanical pipeline construction works") and boiler installation and painting construction works (hereinafter "the boiler construction of this case") among B construction works subcontracted by Defendant Gyeong-nam Co., Ltd. (hereinafter "Gyeong-nam Co., Ltd.") prior to the filing of the lawsuit: 3,524,668 dollars and delay damages therefrom:

1) The construction cost of USD 5,057,955 refers to USD 1,946,556 (hereinafter “$”) for machinery pipeline construction work.

(2) 3,111,399 US$ 2) Additional construction costs for boiler installation and painting construction (2.00 US$ 1,66,710 US$ 3) Additional construction costs (2.00 US$ 2,000) (2) Additional construction costs for raw material-type parts, defective materials provided by Gyeongnam company, modified construction costs due to design errors, etc., 1,666,710 US$ 1,467,878 US$ 4) Additional construction costs for public design and expendable materials, 209 US$ 209,294 US$ 5) unpaid local purchase subscription costs of 308,212 US$ 231,160, ② Additional construction costs for raw material-type parts, US$ 7,052 US$ 6) from 8,710,049 to 35,185,361,645 US$65,685,6365).

B. In relation to the construction of the instant case, Gyeongnam Company claimed the following items and details related to the instant construction and damages for delay as a counterclaim.

1) USD 1,929,039 for the settlement of construction cost between the Plaintiff and Gyeongnam-si ($ 2) 1,824,678 for the remainder of the other items ($1,824,678 for the compensation for delay concerning the pressure test process of the boiler construction in the instant boiler, for the re-purchase of cargo materials within the boiler construction in the instant boiler construction, for the removal of cargo from the Plaintiff, for the removal of steel products

C. 1) Items A through 4 as mentioned above among the main claims of this case are cited in whole or in part, 5) 1.