(영문) 대전지방법원 2018.02.01 2017구합102807
부당해고구제재심판정취소
Text

1. The plaintiff's claim is dismissed.

2. The costs of the lawsuit, including costs incurred by participation, are all assessed against the Plaintiff.

Reasons

1. Details of the decision on retrial;

A. The Intervenor Intervenor B (hereinafter referred to as the “ Intervenor”) entered the Plaintiff on December 9, 2008, and the Intervenor C entered the Plaintiff on July 16, 2008, respectively; the Intervenor B was the business support team leader; and the Intervenor C was the business support team leader; and the Intervenor was the business support team leader; and the Intervenor is affiliated with the branch of the National Public Research Union A.

B. On July 7, 2016, according to the resolution of the Personnel Committee (hereinafter referred to as the “Personnel Committee”), the Plaintiff: (a) on July 11, 2016, (b) participated in the workshop event with six outside persons present at the conference on the day immediately before the event, and (c) participated in the workshop event after obtaining the signature of six outside persons present at the conference on the day immediately before the event; (b) carried out a package trip without proceeding as a schedule; (c) on July 11, 2016, the Plaintiff prepared the workshop as if he/she carried out the workshop with the signature of outside persons and group pictures received at the conference on the next day; and (d) made a false report as to the result of the event’s dismissal without any prior approval; and (d) made a false report on the result of the event’s dismissal; and (e) made a false report on the result of the event’s dismissal without any prior approval.

(hereinafter “each of the instant disciplinary actions”). C.

The Intervenor and the Korean Public Research and Trade Union have filed an application for remedy with the Chungcheong Regional Labor Relations Commission because each of the disciplinary actions in this case constitutes unfair disciplinary action and unfair labor practice.

On December 19, 2016, the Chungcheongnam-nam Regional Labor Relations Commission has accepted the part concerning the unfair disciplinary action on December 19, 201, which was the disciplinary action against the intervenors on July 13, 2016.