Text
1. The Defendants jointly hold the Plaintiff KRW 56,108,989 and the interest rate of KRW 24% per annum from June 23, 2020 to the date of full payment.
Reasons
1. Comprehensively taking account of the purport of the entire arguments in Gap's evidence Nos. 1 through 4, 6 through 9, Eul's evidence Nos. 12-1, and 2 as to the cause of the claim, the plaintiff entered into a contract with the defendant, on March 8, 2019, for which the construction cost is KRW 50 million and interest rate of KRW 24% per annum at the time of delay in the payment of the above construction cost (hereinafter "the contract of this case"). The plaintiff entered into a contract with the defendant, on August 1, 2019, for which the contract of this case was received by the defendant, with the construction cost of this case 30 million won and KRW 10,000,000,000 and KRW 10,000 are 30,000,000,000,000,000 won and KRW 10,000,000,00,000.
According to the above facts, the defendants are jointly obligated to pay damages at the rate of 24% per annum as stipulated in the contract of this case from June 23, 2020 to the date of full payment, unless there are special circumstances. The defendants are jointly obligated to pay damages at the rate of 56,108,989 won for the remainder of the construction payment (30 million won for the construction payment of this case - the construction payment of 243,891,010 won) and the copy of the complaint of this case to the defendants.
2. Judgment on the defendants' assertion
A. The Defendants’ assertion differs from the actual construction cost agreed in the course of requesting the Plaintiff, a specialized construction company holding a comprehensive construction license, to conduct a completion inspection.