Text
A person shall be punished by imprisonment with prison labor for not less than four months for a crime of No. 1 in the judgment of the defendant, and imprisonment with prison labor for not more than four months.
(b).
Reasons
Punishment of the crime
[Criminal Power] On July 15, 2010, the Defendant was sentenced to a suspended sentence of three years on the grounds of imprisonment for the violation of the Act on the Aggravated Punishment, etc. of Specific Economic Crimes (Misappropriation) in the Daejeon District Court Support on the Aggravated Punishment, etc. of Specific Economic Crimes, and the judgment became final and conclusive on November 20,
1. The Defendant is a person who has been engaged in construction business under the trade name called C from January 1, 2009 to April 1, 2010.
On December 31, 2009, the Defendant made a false statement to the victim G at the E- (alias F) office located in Seo-gu, Seo-gu, Seo-gu, Chungcheongnam-gu, Chungcheongnam-gu, stating that “The Defendant is obliged to pay the construction cost in advance, but there is no money at this time, and he will repay it after lending KRW 25 million.”
However, at the time, the above C had a loan to the Construction Mutual Aid Association amounting to KRW 80,00,000 and KRW 100,000,000,000,000,000,000 won, and there was no intention or ability to pay money from the victim because the Defendant did not own property, even if it did not have any intention or ability to pay money.
The Defendant received KRW 25 million from the victim to the account in the name of Korea-U.S.-U.S.M. on the same day.
2. The Defendant, around November 15, 2011, lent the amount of construction cost of KRW 20 million until March 8, 2012 to the Defendant, if he/she loans KRW 20,000,000 as he/she planned to do so to do so from the bank of the operation of He/she is the victim of He/she of He/sheung-gu, Chungcheongnam-gu, Chungcheongnam-gu.
As security, the third priority right (the highest claim amount, KRW 36 million, the mortgagee M) established on the land will be cancelled. The third priority right (the highest claim amount, KRW 36 million, the mortgagee M) will be cancelled.