(영문) 부산지방법원 2017.07.12 2015가합47115
부당이득금
Text

1. The Defendant (Counterclaim Plaintiff) paid KRW 537,00,000 to the Plaintiff (Counterclaim Defendant) and its related amount from October 3, 2015 to July 12, 2017.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. Basic facts

A. The Plaintiff and the Defendant are both companies operating real estate development business, etc., and the Defendant changed the trade name from C to B corporation on November 5, 2015.

D is a person who works as a defendant's internal director from July 30, 2012.

B. 1) The Defendant’s construction of collective housing and ancillary and welfare facilities (hereinafter “instant project”) on the 53 parcel outside Busan Shipping Daegu E, Busan.

(2) On May 31, 2015, the Plaintiff entered into a contract with F Co., Ltd. (hereinafter referred to as “F”) that acquired the instant business (hereinafter referred to as “instant transfer/acquisition agreement”) on behalf of the Defendant, and the main contents thereof are as follows.

1. B (referring to the defendant; hereinafter the same shall apply) on or before June 22, 2015 shall complete the receipt of documents by changing the said project undertaker from CF to A, a stock company;

2. ① Conclusion of a separate sales contract (referring to the Plaintiff, referring to the Busan metropolitan Daegu G; hereinafter the same shall apply) with G (referring to the Plaintiff; hereinafter referred to as the “G”) and a building not registered on the ground, ② conclusion of a separate agreement with D (referring to the Busan metropolitan Daegu H; hereinafter referred to as the “H”) with D (referring to the 2,290,000,000), which is a person holding the provisional registration; ③ change the said project proprietor from C Co., Ltd to A from C Co., Ltd. to D; ④ conclusion of a separate sales contract (referring to the 8.10,000,000,000,000,000,000,0000,000,000,000,000,000,000,000,000,000,000,000,00,000,00,00,00,00.

3. (1) Transfer of ownership and completion of surrender under the sales contract, including buildings not unregistered on G land and ground, and H.

arrow