(영문) 제주지방법원 2015.08.28 2014가단5363
추심금
Text

1. The Defendant: KRW 44,989,314 for the Plaintiff and KRW 5% per annum from April 11, 2014 to August 28, 2015.

Reasons

1. Basic facts

A. The Plaintiff is a corporation whose business purpose is to manufacture and sell concrete (mixed) and upon receiving a request from B Co., Ltd. (hereinafter “B”) from October 20, 201 to January 19, 201, the Plaintiff supplied 62,988,000 won at the site of new construction of apartment units corresponding to D parking lots in Jeju, which are constructed by B, and was not paid 46,08,000 won among them.

B. The Plaintiff filed a payment order against B with the Jeju District Court No. 201j3425 stating that “B shall pay to the Plaintiff the amount of KRW 46,08,00 and the amount calculated at the rate of 20% per annum from the day following the delivery of the original copy of the payment order to the day of full payment.” On November 30, 2011, the Plaintiff received the said payment order from the Jeju District Court, and the said payment order was served to B on December 7, 2011, and was finalized on December 22, 2011.

C. The Plaintiff, based on the original copy of the final and conclusive payment order as mentioned above, filed an application for the seizure and collection order with the Jeju District Court No. 2013T as the obligor B, the Defendant as the garnishee, and received the seizure and collection order from the Jeju District Court on September 25, 2013. The claim claims amounting to KRW 46,08,00, and damages for delay calculated at the rate of 20% per annum from December 8, 2011 to September 17, 2013, calculated at the rate of 16,414,904, totaling KRW 45,680, totaling KRW 62,548,58,584, and KRW 17,59,270, which was distributed to the Plaintiff as the obligor. The Plaintiff’s claim is one of the construction works executed with the Jeju District Court on June 28, 2013, with the amount of KRW 17,559,270 (hereinafter “the construction work price”).

The order of seizure and collection of the above Jeju District Court 2013TTTT 5832 was served on the defendant on September 27, 2013.

[Grounds for recognition] without dispute;