Text
1. As to KRW 23,818,670 among the Plaintiff-Counterclaim Plaintiff and KRW 20,000,100 among the Plaintiff-Counterclaim Plaintiff, the Plaintiff-Counterclaim Defendant (Counterclaim Plaintiff) was on January 28, 2014.
Reasons
Basic Facts
On June 8, 2012, the Plaintiff entered into a contract with the Defendant on June 8, 2012, under which the Plaintiff shall newly construct a 4-story building on the land of Suwon-si, Suwon-si, 216.7 square meters, which is owned by the Defendant, until October 31, 2012, and the Defendant shall pay the construction cost of KRW 400 million (A evidence 1; hereinafter “instant contract”).
At the time of the conclusion of the instant contract, the original Defendant agreed on the contents other than drawings, but did not have any additional amount in addition to the agreed terms. On the other hand, unlike the contents of the initial construction permit, the said building was to be newly built by dividing the said building into five households, studio three households, and 1 commercial buildings, and among which, the studio construction was agreed after the completion of the building.
The defendant, on June 9, 2012, KRW 100,000,000 for the plaintiff, KRW 22,000,000 for the same year.
7.3.5 million won, 13.4 million won for the same month, 31.1 million won for the same month, and the same year;
8. 10.5 million won, 22.2 million won in the same month, and the same year;
9. 11. 20 million won, KRW 10 million on the 21th of the same month, KRW 2.1 million on the 22th of the same month, KRW 10 million on the 10th of May of the same year, KRW 10 million on the 12th of May of the same month, KRW 5 million on the 13th of the same month, KRW 5 million on the 16th of the same month, KRW 17.15 million on the 16th of the same month, KRW 5 million on the 20th of the same month, KRW 5 million on the 24th of the same month, KRW 3 million on the 26th of the same month, KRW 10 million on the 29th of the same month, KRW 50 million on the 5 million on the 24th of the same month, KRW 5 million on the 29th of the same month, KRW 500,00 on the 111.5 million on the same month;
3. Five million won, and the same month.
6. 3 million won, KRW 50 million on the 29th of the same month, KRW 1.5 million on the 30 million on the 30th of the same month, KRW 1.1 million on the 14th of the same month, and KRW 3.6 million on the 14th of the same month.
On December 11, 2012, the defendant obtained approval for use for the said new building, and completed registration of preservation of ownership on the 14th of the same month.
On the other hand, D on April 6, 2012 and the same year
5. 4. The Plaintiff was prepared and delivered a notarial deed based on a monetary loan worth KRW 40 million. On November 7, 2012, the Plaintiff’s claim for construction price against the Defendant as the obligor, and the Defendant as the third obligor is Suwon District Court 2012TTB4024.