Text
1. The Defendant shall pay to the Plaintiff KRW 79,837,677 and the interest rate of KRW 15% per annum from October 31, 2017 to the date of full payment.
Reasons
1. Facts of recognition;
A. The following facts may be acknowledged either in dispute between the parties or in Gap evidence Nos. 1-10 (including a serial number; hereinafter the same shall apply) by taking into account the overall purport of the pleadings:
(1) The Ctel association is an organization established to newly construct and sell commercial buildings, etc. on the ground by anyone who has the right to purchase commercial land in relation to the D's housing site development project at the time of the implementation of the D's housing site development project. The plaintiff is a member of the above association.
(2) On December 23, 2010, the Plaintiff and a notary public entrusted a law firm E with the said law firm’s commission, and drafted a notarial deed of a monetary loan agreement (hereinafter “notarial deed of this case”) with the content that the Ctel association shall pay 81,527,661 won borrowed from the Plaintiff on December 13, 2010 by the Plaintiff until January 31, 2011, and if delay, it shall pay 20% interest per annum from the next day to the date of full payment (hereinafter “instant notarial deed”).
2. Total purchase price and payment method (1) : (2) 2.7 billion won (including value-added tax): 7.72 billion won (including value-added tax): 7.2 billion won (payment within 45 days after the transfer of ownership and the registration of trust) (3) the first intermediate payment: 27.28 million won (payment within 4.5 days after the transfer of ownership and the registration of trust): 2.777 billion won (payment within 5 days after the registration of transfer of ownership): 50 million won (payment within 50 days after the registration of trust) in G court’s judgment amount, 2.77 billion won (payment within 50 million won after the date of delivery to B (Defendant)): 3.5 billion won (payment within 30 days after the completion of the construction).
3. The terms and conditions of sale (1) A (Ctels Association) shall fulfill this contract.
(3) The name of a building under construction and the change of its owner shall be transferred without delay through a lawsuit.
(4) Any balance shall be.