(영문) 서울동부지방법원 2014.08.01 2013가합10442
추심금
Text

1. Defendant K shall have the Plaintiff KRW 4,783,818 respectively, Plaintiff C 4,823,245 won, and Plaintiff E.

Reasons

1. The facts following the facts are as follows: (a) between the plaintiffs and defendant K, pursuant to the main text of Article 150(3) and the main text of Article 150(1) of the Civil Procedure Act, Defendant K led to confession; and (b) among the defendants other than the plaintiffs and defendant K, it may be acknowledged in full view of the overall purport of the arguments as to the evidence No. 1-1 through No. 5.

Although the plaintiffs are not admitted to the membership status of the project of this case with the AD Housing Association Promotion Committee (hereinafter "Promotion Committee") for the purpose of the project of constructing a partnership apartment (hereinafter "the project of this case") with AC and seven parcels in Nam-si, Nam-si (hereinafter "the project of this case"), the plaintiffs succeeded to the status of AE which entered into a contract with the Promotion Committee around December 2003, and they succeeded to the contractual status of AG which succeeded to the contractual status from AF which entered into a contract with the Promotion Committee prior to January 1, 2004, and the plaintiff Eul succeeded to the contractual status of AG which entered into a contract with the Promotion Committee, and around January 1, 2010, from AH which entered into a contract with the Housing Association as seen below, or from the person who acquired the claim of the contract with the Housing Association or the person who entered into a contract with the Promotion Committee, the defendants are members of the Housing Association as seen below for convenience).

B. As to the construction of partnership apartments between the promotion committee and the applicants applying for joining the housing association in the planning to build partnership apartments on the land outside AC and seven parcels at the Namyang-si, Namyang-si, the progress of the project in this case.

(C) Article 2 (Indication of Objects): 32.26 square, and 76 households (pre-determineded). (2) The supply price of each unit determined at the time of project approval shall be determined by multiplying the average supply price per unit by the size of each unit determined at the time of project approval. (3) The number of units shall be later divided into a Han River.