A defendant shall be punished by imprisonment for two years.
Reasons
Punishment of the crime
1. (2010 Highest 7203 instant case) F is a representative director of G stock company aimed at advertising agency business, real estate leasing business, etc. (hereinafter “G”), public relations planning and related consulting business, and real estate selling and leasing business, etc. (hereinafter “H”), and the Defendant is a director of H.
Around May 4, 2006, the Defendant and F came to know that I had difficulties in proceeding with the instant project due to financial shortage while receiving a request for the advertisement of the sale of an officetel on eight parcels of land, such as Seoul Seocho-gu J, K, L, L, M, N,O, P, Q, etc. (hereinafter “instant project site”). Around September 4, 2006, the Defendant and F entered into a contract with R Co., Ltd. (hereinafter “R”) to take over the instant project site under the name of acquisition of the right to implement the instant project, but the acquisition agreement was rescinded because the Defendant and F did not pay the price for the instant project site, and the Plaintiff and F did not enter into an agreement on the sale of the instant project site with the landowners of the instant land, as if they were aware of the investment in the instant project site under the name of the Plaintiff’s intent to receive the investment in the instant project and the investment in the instant site under the name of the investment in the instant project site, and did not have any capacity to receive the investment in the instant site under the name of the Plaintiff and investors.
A. The Defendant and F shall be the 20th floor G of Seocho-gu Seoul Metropolitan Government S Building around September 2006.