(영문) 인천지방법원 부천지원 2015.01.06 2014고단2791
사기
Text

Defendant

A Imprisonment with prison labor for six months, and for one year and six months, respectively.

provided that this ruling has become final and conclusive.

Reasons

Punishment of the crime

1. The Defendant B is a vinyl with the trade name of “H” located in Kimpo-si, Kimpo-si, and a business operator who actually operates the construction company.

Defendant

A is a farmer selected as a subsidy program operator of eco-friendly certification plant cultivation project implemented in Kimpo-si.

《김포시 보조사업》 이하에서는 별지 범죄일람표 중 연번 4, 10, 11, 15와 관련된 부분은 삭제하였다.

It is a farmer selected as a subsidized business operator of the 201 201 Facilities Won, J, K, and L, which is promoted as part of a new and renewable energy business by the Ministry for Food, Agriculture, Forestry and Fisheries as a part of a new and renewable energy business.

M, N,O, P is a farmer selected as a subsidized project operator of the project in 2012.

The above Druper Support Project is to select a farmer who intends to install a Druper for the efficient use of energy by facility cost farmers as a subsidized project operator, and in the case of the project in 2011 where the relevant farmer installs Druper, 30% of the total project cost shall be paid to the local government, 30% of the total project cost shall be paid to the local government, and the remainder 40% (20% shall be 3.0% per annum in the Nonghyup Bank, 3.0% per annum in the Nong Bank, and 7% per year in the case of the project in 2012, 20% of the total project cost shall be paid to the subsidized project operator, and 30% of the total project cost shall be paid to the local government, and the remainder 50% (30% per annum in the Nong Bank shall be 3.0% per annum in the year and 7% per annum in the year) shall be borne by the subsidized project operator.

Defendant

B and the above subsidized project operators are aware that they should bear 40% of the project cost in the case of 2011 and 50% of the project cost in the case of 2012. However, the above subsidized project operators bear their own contributions.

arrow