(영문) 대전지방법원 천안지원 2014.02.06 2012고단1527
업무상과실치상
Text

The Defendants are not guilty. The Defendants are not guilty, and the summary of each of the above acquittal judgment is publicly announced.

Reasons

1. The summary of the facts charged [2012 Godan1527] Defendant B is the Deputy Director of Management of E Co., Ltd. located in Asan City H (for the purpose of production of aggregate). Defendant A is the production unit of the foregoing company; Defendant A is the production unit of E Co., Ltd.; Defendant E Co., Ltd., Ltd., Ltd., which flows out from the container container located in E Co., Ltd., E Co., Ltd., by requesting maintenance to I; on April 29, 2012, four persons, including the victim J(53) who is an I employee, were visiting and repairing the machinery; Defendant B was in charge of the management and safety of E Co., Ltd.’s employees, including Defendant A, and I’s employees at the repair site; Defendant A was in charge of the operation of the container being repaired in accordance with the direction of Defendant B.

When any work, such as maintenance, cleaning, replacement, etc. of machinery, is likely to cause danger to workers, the operation of the machinery shall be suspended; when the operation of the machinery has been suspended, necessary protective measures, such as installing a locker device and a signboard, shall be taken to prevent others from driving the machinery; safety control officials shall maintain the site in order to ensure that those who have access to the repaired machinery do not have access to the repaired machinery; where the repairing machinery is operated, there was a prior duty of care to prevent accidents by safely operating the machinery; on April 29, 2012, at the E-factory around 08:00, Defendant B did not take protective measures, such as installing a locker or sign, which prevents others from working; and Defendant B and Defendant B did not take measures to prevent access to the surrounding area of the repairing machinery before the repair is performed.

arrow