Text
1. On December 4, 2012, with respect to the new construction of a building described in the separate sheet between the Plaintiff (Counterclaim Defendant) and the Defendant (Counterclaim Plaintiff).
Reasons
A principal lawsuit and counterclaim shall also be deemed a principal lawsuit and counterclaim.
1. Date of the commencement of the standard contract for private construction works: The contract price for the completion of April 30, 2013: VAT 10,000,000 won (Won 380,000,000 won): 60,000 won intermediate payment after the installation of concrete concrete units of the first floor: 60,000,000 won after the installation of concrete units of the second third floor concrete units of the third floor, and 60,000,000 won after the completion of the work: the payment rate for delayed payment shall be 60,00,000,000 won after the completion of the work at the fourth stage of April 10, 200: 1,000 won after the completion of the work at the second stage of the work at the expiration of the construction work at the expiration of the first time, and the defendant shall notify the plaintiff of the completion of the construction work at the expiration of the construction work at the expiration of the term of force majeure or war;
Article 27 (Compensation for Delay) (1) When the defendant fails to complete construction within the deadline for completion, he/she shall pay to the plaintiff the amount calculated by multiplying the contract amount by the rate of the compensation for delay in the written contract by the number of days
Provided, That where a completion inspection has been delayed due to a cause attributable to the plaintiff and where the construction has been delayed due to any cause falling under any of the following subparagraphs, the compensation for delay equivalent to the number of relevant days shall not be paid:
1. Cases due to force majeure events prescribed in Article 18;
2. Where it becomes impossible to carry out construction works because the supply of important materials that the defendant could not use as a substitute has been delayed due to the plaintiff's negligence responsible for him/her.
3. Where the commencement of construction has been delayed or suspended due to causes attributable to the plaintiff;
4. Where Corporation is delayed due to any other cause not attributable to the defendant.
A. On December 4, 2012, the Plaintiff entered into a contract with the Defendant for the construction of a new building as indicated in the attached Table (hereinafter “instant construction”) with respect to the construction of a new building as indicated in the attached Table, as follows:
hereinafter “instant contract”).