(영문) 의정부지방법원 2019.04.16 2018가단122700
손해배상(기)
Text

1. The plaintiffs' claims are dismissed.

2. The costs of lawsuit are assessed against the plaintiffs.

Reasons

1. Facts of recognition;

A. The defendant is a person who resides in D Apartment E in the Gu Government-si, and the plaintiffs are the persons who resided in F, the defendant's apartment.

(Plaintiffs moved to directors in the above apartment house during the instant lawsuit).

The plaintiffs, around March 2018, known that the defendant was suspected of water leakage in the defendant's apartment, while my cocoi in his apartment was discovered.

Accordingly, the plaintiffs and the defendant agreed that "the defendant directly ordered and processed water leakage works, and the interior works of the plaintiffs' apartment complexes and the construction works, which occurred as a result of water leakage, shall be paid by the defendant after ordering the plaintiffs' direct construction works," and the defendant entrusted the business of "G" located in the city of the government, with the completion of the primary water leakage works.

After the completion of the interior and drawing works as requested by the plaintiffs after the first water leakage works, the defendant transferred 3.80,000 won to the Indianian business operator on April 4, 2018, and 1.2 million won to the Captain on April 5, 2018.

C. Since the first water leakage work, the Plaintiffs and the Defendant agreed on the same conditions as the first water leakage work, and the Defendant requested G to implement the second water leakage work.

After the second water leakage works, the plaintiffs completed the interior and drawing works as requested by the plaintiffs, the defendant transferred the 90,000 won to the Rotterdam business operator on May 16, 2018, and 10,050,000 won to the Rotterdam business operator on May 10, 2018.

The Plaintiffs filed the instant lawsuit that this case occurred due to mycoi in addition to water leakages after the second water leakage works.

As a result of the appraisal conducted in the instant litigation procedures, water leakage does not occur any more after the second water leakage works. Fung occurring in the apartment of the Plaintiffs, rather than giving rise to water leakages, it is necessary to build a damp part due to water leakages after the second water leakage works, and to provide water to remote areas in which the Plaintiffs have not been sufficiently built.