Text
1. The plaintiff's claim is dismissed.
2. The costs of lawsuit shall be borne by the Plaintiff.
Reasons
Details of the disposition
The Plaintiff is an individual entrepreneur engaged in construction waste collection and transportation business, etc. with the trade name of “B,” and for the purpose of “temporary storage of construction waste,” and 1,525 square meters (hereinafter “instant land”) out of 3,446 square meters in Gangseo-gu Seoul Metropolitan Government, Gangseo-gu (divided on October 16, 2012 and converted into 3,330 square meters (hereinafter “instant land”), D previous 225 square meters (divided on October 16, 2012 and converted into 98 square meters; hereinafter “instant land”); 188 square meters in E previous 863 square meters (hereinafter “instant land”); the period of temporary use of farmland from the Defendant on March 14, 2006; and the period of temporary use of farmland to restore to its original state to its original state until June 30, 2009; and the period of temporary use of farmland to be agricultural management to its original state to its original state to its original state to its original state to its original state to 30.5.31.5.
On February 17, 2012, the Plaintiff filed an application for permission to engage in development activities with respect to land ① and ② land, after deliberation by the Gangseo-gu Urban Planning Committee, on April 17, 2012, for the purpose of “use as a construction waste collection and transportation storage place after changing the form and quality of land.” However, the Defendant rejected the application on the ground that “the construction of the relevant facilities pollutes the surrounding environment due to the construction of the relevant facilities, and it is impossible to install the facilities due
On June 26, 2013, the Plaintiff appealed and filed a lawsuit with the Seoul Administrative Court to revoke the revocation of the permission for development activities on June 26, 2013. However, on March 7, 2014, the Plaintiff filed a lawsuit to revoke the revocation of the permission on development activities: ① the land category was transferred, ② the land category is located in the natural green area; ② the construction waste storage facilities in the instant case; ② the environmental pollution is likely to occur due to noise, vibration, dust, etc. in the surrounding area; ③ the instant case and ② the land adjacent to the land.