(영문) 수원지방법원성남지원 2015.06.25 2013가합7123
손해배상(기)
Text

1. All of the plaintiff's claims are dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On January 27, 1995, Non-party B’s land sales contract and building permit 1) Non-party B is limited to “C” when indicating a lot number of the Gyeonggi-gun C (hereinafter referred to as “C”).

) The land D, E, F, G, H, and I (hereinafter “each of the instant land”).

3) Multi-household housing in this case (hereinafter “multi-household housing in this case”)

(2) At the time of the sale of each of the instant land, B and J agreed to obtain a construction permit under the name of Nonparty 2, E, G, H ground Nos. 1 and 2, and 16 households (hereinafter “Dong”) among the instant multi-household housing, under the name of Nonparty 2, who are the births of the shape B, to sell each of the instant land, and upon entering into a sales contract with the effect that one of the instant multi-household housing is to purchase the said multi-household housing and to be additionally paid KRW 270,000,000,000,000,000.

3) Under the above agreement, B completed the registration of ownership transfer with respect to G and H land on August 21, 1996, and on March 14, 1997 under the name of each K. On September 23, 1996, J borrowed a construction permit under the name of B for 15 multi-household houses in the name of D, E, G, and H, respectively, and started the construction of the instant multi-household house. (B) J and K start the construction of the instant multi-household house. (3) around November 29, 196 in order to raise the construction cost of the instant multi-household house, J and K borrowed KRW 1950 million from Nonparty L and M (hereinafter “L”) and at the time of borrowing KRW 10,500,000 from the issuer and issuer of the instant multi-household house and KRW 19,50,000,000 from the issuer and issuer of B and KRW 197,150,000,00.