(영문) 서울중앙지방법원 2017.11.13 2017가단5031978
손해배상(기)
Text

1. The Defendant’s KRW 152,952,570 for the Plaintiff and the following: 5% per annum from May 14, 2012 to July 28, 2017.

Reasons

1. Basic facts

A. On December 10, 2001, the head of Eunpyeong-gu Seoul Metropolitan Government (hereinafter “the head of Eunpyeong-gu”) authorized the implementation plan of the road construction work to ensure that the residents using the existing road do not suffer from inconvenience (a project operator: the head of Seoul Special Metropolitan City Mayor and the Mayor of Seoul Special Metropolitan City; hereinafter the “Defendant”) and publicly notified the implementation plan of the road construction work in order to ensure that the existing road is incorporated into the exclusive road for motor vehicles in order to newly build or expand the exclusive road for motor vehicles by the Eunpyeong-gu Seoul Metropolitan Government as a Eunpyeong-gu announcement B of Eunpyeong-gu.

B. Accordingly, in order to acquire the site of the instant road project, the Defendant acquired the answer 286 square meters and 123 square meters (hereinafter “each of the instant land”) from the deceased F (Death on December 14, 201, hereinafter “the deceased”) on May 14, 2002 in accordance with the former Act on Special Cases Concerning the Acquisition of Land for Public Use and the Compensation Therefor (repealed by Act No. 6656, Feb. 4, 2002; hereinafter “the Public Special Act”), and completed the registration of ownership transfer on the ground of sale under the name of the Defendant.

C. On February 25, 2004, the Defendant announced the designation of the Nan Urban Development Zone and the development plan for the development of the Nan Urban Development Zone in the order of its implementation by dividing it into 1, 2, and 3 districts with respect to the land of Eunpyeong-gu Seoul Metropolitan Government Ldong and Mdong, and the land of 3,495,248 square meters in the Eunpyeong-gu Seoul Metropolitan Government public notice on February 25, 2004 (the project implementer is called the Seoul Housing Corporation (the Seoul Housing Corporation, the Seoul Housing Corporation, the hereinafter referred to as

[) On December 20, 2004, a public announcement of Seoul Special Metropolitan City announced a "authorization of an implementation plan for construction sections for the N urban development zone one zone and bypass roads" on December 20, 204, and on December 30, 2005, a public announcement of Seoul Special Metropolitan City announced P for the establishment of a development plan for N urban development zones and authorization of an implementation plan for a zone 1, 2