(영문) 서울남부지방법원 2015.03.06 2014가합13243
물품대금
Text

1. The Defendant amounting to KRW 220,717,140, and KRW 6% per annum from September 1, 2012 to February 18, 2015 to the Plaintiff.

Reasons

1. From May 1, 2012 to July 31, 2012, the Defendant entered into a contract for the clinical processing of clothing with the Plaintiff, and received goods equivalent to KRW 233,872,630, which the Plaintiff was processed in his/her discretion pursuant to the said contract, but did not pay KRW 158,023,740, out of the clinical processing costs. The Defendant ordered the Plaintiff to perform the clinical processing of goods equivalent to KRW 62,693,40, and ordered the Plaintiff to pay the price, and thus, the Defendant did not pay the price. Accordingly, from September 1, 2012 to February 18, 2015, the delivery date of the written complaint of this case, 6% per annum under the Commercial Act, and damages for delay by public notice under Article 208 (3) of the former Civil Procedure Act, based on each of Article 208 (3) of the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings.

arrow