(영문) 대전지방법원천안지원 2016.10.18 2014가단111500
손해배상(기)
Text

1. The Defendant’s KRW 47,817,00 for the Plaintiff and KRW 5% per annum from December 2, 2014 to October 18, 2016.

Reasons

1. Basic facts

A. On March 15, 2012, the Plaintiff: (a) planned a new construction of “C Civil Service Administrative Center” (hereinafter “instant building”); (b) conducted a bid for the design service; and (c) entered into a contract with the Defendant who participated in the said bidding on March 15, 2012, stipulating that KRW 48,010,000 of the design cost for the instant building will be the cycle of design service (hereinafter “instant design service contract”); and (d) the main contents are as follows.

The division shall include all matters, such as the permission for the entry and construction of facilities, such as the plan design including the details of increase in size 400 400 400 400 400 400 m20 400 m20 m20 m20 3rd floor, the civil petition administrative center for the purpose of the 4th floor of the second floor, the office of health branch office, the head office, the council room, the residents' self-governing center, the council room, the council hall, the council hall, the council hall, and the building of the m2nd floor.

In preparation for future expansion: To establish and reflect the prior measures to prepare for the anticipated part of the extension (such as design under consideration of expansion, transfer of Exes, etc.) in consideration of the plan for the extension of the facilities in accordance with the basic plan.

B. On July 10, 2012, the Defendant modified the instant design service contract with the Plaintiff, and its main contents are as follows.

It includes all matters, such as permission for entry and rescue facilities, so that all stages can be promoted through the next extension of the interim implementation plan for the plan, design, and construction of a gold club, including the following changes in size 163.55, 295.76 468.14, and the interim implementation plan for the plan, design, and construction of a gold club, including the plan, design, and the construction of a gold club, for the purpose of the 3th floor of the 1st floor, warehouse, machine room (exclusive use), civil service administrative center, health and branch office, the head of Dong, the meeting room, the meeting room, the residents' self-governing center, the meeting room's community service

(The basic design for the re-construction shall be taken into consideration 4 floors)

C. On September 5, 2012, the Defendant completed the instant design service, and the Plaintiff paid KRW 48,010,000 to the Defendant.