Text
1. The part against the defendant in the judgment of the first instance shall be revoked;
2. The plaintiff's claim against the defendant is dismissed.
3...
Reasons
1. On the same day, the Defendant, who was the representative of the said company, has jointly and severally guaranteed all obligations owed by the said company to the said bank due to the use of the relevant credit card.
The above bank and the above company agreed at the 12th day of each month to pay credit card bills, and the term of validity of issued credit cards was June 30, 2006.
On February 28, 2007, Han Bank transferred all of the credit card payment claims (principal 2,004,310 won) and rights incidental thereto to the credit card payment claims against B to the promotion mutual savings bank company, and notified the above assignment of claims to B by content-certified mail.
On November 30, 2011, the above claims against B were transferred to the limited partnership loan, and on August 8, 2013, to the limited liability company Hanwon loan. The above mutual savings bank and each of the above limited liability companies notify each of the above claims assignment to B by content-certified mail on February 3, 2015.
As of January 27, 2015, the balance of the above bonds that the Plaintiff acquired is the total of KRW 2,004,310, interest KRW 5,587,580, and KRW 7,591,890.
[Ground of recognition] Facts without dispute, entry of Gap evidence Nos. 1, 2, and 3, purport of the whole pleadings
2. According to the above facts of recognition, the Defendant is obligated to pay the Plaintiff, the transferee of the joint and several surety bond, the principal and interest of the claim acquired, KRW 7,591,890, and delay damages for the principal amount of KRW 2,004,310, barring special circumstances.
Therefore, the defendant's defense that the above credit card was extinguished by the statute of limitations. According to the above facts, it is reasonable to view that the due date for the credit card user's credit card payment claim of this case is August 12, 2006, which appears to be the due date for the payment of the user's credit card by the due date. The plaintiff's application for the payment order of this case is filed.