(영문) 서울중앙지방법원 2015.08.11 2015고합128
특정경제범죄가중처벌등에관한법률위반(사기)등
Text

A defendant shall be punished by imprisonment for three years.

Reasons

Punishment of the crime

1. The normal process of winning a contract through the National Integrated Electronic Procurement System of the Public Procurement Service (hereinafter referred to as the “FO”) shall be as follows:

The finance officer who is a public official in charge of tendering in the local government who is the place of ordering the facility construction shall clearly announce the basic matters of the facility construction, such as the basic amount of construction, the scope of reserve price (the assessment rate, and the basic amount

B. The finance officer access to the national funeral server with an authenticated finance officer’s PC, thereby creating 15 examples within the limit of 3% of the construction basic amount 【within the limit of 15%, mixing with the lottery numbers corresponding to 15 examples, combined with the finance officer’s authentication certificate, and encrypted it with the finance officer’s authentication certificate, and then transmitting and storing 15 examples and lottery numbers to the national funeral server. However, the finance officer’s explanation of the process is entirely unaware of what the number of winning numbers correspond to the finance officer’s winning numbers.

(c) For bidders, above:

(a) After confirming the content of the notice in paragraph (1), input a bid using a bidder PC, and if two of the 15 empty spaces are selected at will, the value will be stored in the national funeral system server.

Upon the expiration of the bid period, the national flag shall determine the estimated amount by averaging the estimated amount by the winning prices corresponding to the highest four winning numbers among the winning numbers of lottery tickets selected automatically by the bidder, and shall be calculated by multiplying the estimated amount by the bid rate (87.745% in the case of local governments: 87.745% in the case of local governments, 1 billion won or more in the construction cost, but less than five billion won: 86.745% in the case of local governments, 86.745% in the case of local governments, 5 billion won or more in the construction cost: 85.495% in the case of 85.495% in the case of 10 billion won or more, and 79.95% in the case of local governments).

(e) The treasurer shall have experience in performing the contract, technical ability, financial status, and confidence in the order of the bidder's bid price in the order of the bid price nearest to the successful bid price, with the estimated bid price of at least the lowest tender price.