logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 서울중앙지방법원 2014.05.14 2012가합528639
공사대금
Text

1. The Defendants shall jointly and severally serve as the Plaintiff KRW 213,66,454 as well as as the period from June 23, 2012 to May 14, 2014.

Reasons

1. The project cost for Article 3 (Raising Funds) of the Basic Facts is to be raised by selling the remaining household units (7 households, 4, 5 floors, and neighborhood lifestyles) of the apartment of this case that the Defendants did not acquire.

1) As of the date of the land injury contract, the mortgage, seizure, and superficies issue as of the date of the land injury contract shall be resolved at the Defendants’ expense before the sale thereof, and shall not interfere with the progress of the project or the sale by the remaining generations, and shall not interfere with the registration of ownership transfer at the time of the completion and sale thereof, by resolving all compensation, compensation, etc. under the Defendants’ responsibility. 2) The Defendants purchased adjacent sites (O, P, Q, R, S, T, and U) for their business and provide the Plaintiff with the same. The Plaintiff shall settle the construction cost calculated with a unit price of 38 million won / 3.3 square meters (p.) per share for the remaining three households (five floors) within three months after the completion of the construction work.

Article 4 (Payment of Construction Costs) (1) The project cost is based on the “detailed statement of construction cost,” which is the amount proposed by the Plaintiff, and the payment of construction cost shall be made on a monthly basis, but the supervisor shall, if the Plaintiff applies for the payment of the completed portion, conduct a performance inspection and report the result to the Defendants within seven days, and the Defendants shall pay the relevant progress payment to the Plaintiff within seven days after receiving the performance inspection report. (2) The Defendants shall pay the construction cost to the Plaintiff up to 70% of the progress of the construction project, and the Plaintiff shall sell the remaining household (three generations) to the remainder of the construction project on behalf of the Plaintiff.

(3) The Defendants and the Plaintiff settled the construction cost within 3 months after the completion of the construction. Article 5 (Implementation of Construction Works) (1) The Plaintiff shall perform responsible construction works for all matters related to the construction project, and shall resolve various civil petitions arising out of the reasons attributable to the business operator during the construction project. (3) The design drawing, which serves as the basis for the contract, is the accompanying design drawing, is the accompanying design drawing, and the execution design is carried out based on this drawing after the completion of the contract.

arrow