Text
1. The Defendant (Counterclaim Plaintiff) paid KRW 10,413,902 to the Plaintiff (Counterclaim Defendant) and its related amount from March 11, 2017 to April 3, 2018.
Reasons
1. Basic facts
A. On March 18, 2016, the Defendant: (a) between the Plaintiff and the Plaintiff on March 18, 2016, for construction work in the part of civil engineering (hereinafter “instant civil engineering work”) among the construction works for the land-based neighborhood living facilities in Busan City (hereinafter “instant construction”) under the name of re-construction; (b) from March 30, 2016 to March 30, 2016; (c) the construction work period of the instant construction work.
5. As of March 31, 2016, the Defendant concluded a construction subcontract with the end of 30,000 won in total, including KRW 59,950,000,00, and KRW 44,000 on April 19, 2016, pursuant to the said contract.
B. Since then, on May 10, 2016, the Plaintiff sought to change the recipient to a LF Industry Co., Ltd., and the Defendant concluded a new construction subcontract between the Plaintiff and LF Industry Co., Ltd. with the construction cost of the instant civil works in the name of LF Industry Co., Ltd. from May 1, 2016 to 30 of the same year, and the construction period of May 13, 2016, the Defendant paid approximately KRW 3,00,000,000 in total to LF Industry Co., Ltd. under the said contract by adding approximately 60,50,000,000, compared to the above construction cost of KRW 42,350,000, Jun. 42, 2016.
C. On June 18, 2016, the Defendant: (a) between the Plaintiff and the Plaintiff on June 18, 2016, with respect to the construction and equipment portion of the instant construction project (hereinafter “the instant aggregate construction project”); (b) the construction cost of KRW 152,00,000 (Additional Tax); and (c) the construction period from June 18, 2016 to the same year.
9. A construction subcontract for the end of 10. d.
The Plaintiff completed all of the instant structural construction on October 24, 2016, but the Defendant did not pay KRW 11,000,000 out of the price for the instant structural construction.
E. The Plaintiff received all claims related to the instant construction from LF Industry Co., Ltd., and notified the Defendant thereof.
[Reasons for Recognition] Facts without dispute, Gap evidence 1, 2, Eul evidence 1, 9-1, 2, Eul evidence 1-1 to 3, 2-1, 2-2, Eul evidence 3-1 to 3, each entry and pleading.