(영문) 서울고등법원 2015.09.02 2015나2003868
공사대금
Text

1. The part against the plaintiff corresponding to the money ordered to be paid under the judgment of the court of first instance shall be revoked.

The defendant.

Reasons

1. The basic facts;

2. The grounds for the statement concerning A, B, and C are as stated in the corresponding part of the judgment of the first instance, except for addition or dismissal as follows:

(The main text of Article 420 of the Civil Procedure Act is to add the evidence of evidence No. 11, No. 6, No. 19, and No. 21 through No. 25 to the evidence of evidence No. 4-10, “The result of the fact-finding on the branch office of the Bank of Korea of the first instance” to the evidence of evidence No. 11, No. 6, No. 19, 21 through 25, and the result of the fact-finding on the second instance two industries corporation

Part 4: 14. (1) The following shall be added:

Bsan awarded a contract to the Defendant for the instant construction works except for civil engineering, construction, and electrical construction.

If the Defendant supplied raw materials, such as steel plates, from the two islands, the instant subcontract is a content that the Plaintiff procure miscellaneous materials, prepares a field room, on-site office, restaurant, and workers’ lodging room, and implements the instant construction project by using human resources and equipment.

The construction work of this case is conducted in the order of manufacturing and installing tanks on the land that the C Company contracted with the construction work of this case from 2.0, and manufacturing and installing approximately 50 electrical corrosion prevention devices per tank in order to prevent corrosion of the tank floor which is a metal material, and installing a cateral line and completing the basic floor construction work again by performing civil engineering work such as rewing, drying and concrete construction, etc., and manufacturing and installing tanks on the land that the Plaintiff completed the basic floor construction work, such as cutting, cutting, melting, painting, sing, etc. of raw materials such as steel plates in the manufacturing site, and manufacturing and installing tanks on the land on which the basic floor construction work is completed.

Part 7 2-5 is high as follows.

7) The Plaintiff requested the Plaintiff to submit the contract performance guarantee and the advance payment guarantee at the latest in order to pay the advance payment to the Plaintiff.