Text
1. The defendant shall be the plaintiff.
(a) Attached 1 drawings on one story above the 281m2.1m2 in Busan Jung-gu, Busan, shall be indicated (1), (2), (9), (0), and (1).
Reasons
1. Basic facts
A. On April 10, 2019, the Plaintiff purchased from D the Jung-gu Busan metropolitan area 281.1 square meters (hereinafter “the Plaintiff’s land”) on April 19, 201, and completed the registration of ownership transfer on April 19, 2019, and constructed an officetel building on the land above.
B. The Defendant is the owner of Jung-gu, Busan, which is adjacent to the Plaintiff’s land, of the 74.84 square meters and 55.04 square meters and 75.04 square meters and 75.04 square meters of the 2nd roof housing (hereinafter “Defendant’s building”).
(c)
(11) Of the Plaintiff’s land, the Defendant building of this case shall carry out the indication of the attached Table 3 drawings (1), (2), (4), (5), (7), (11) 1.2 square meters of land and (9), (1), (1) , (1) , (3) , and (9) 1.5 square meters of land in the ship which successively connect each point of the instant land (hereinafter referred to as “the occupied portion of the instant land”) and shall be subject to the indication of drawings 1,2, (9), (1) , (1), (2) , (1) 15.04 square meters of the above ground, (1), (2) 15.04 square meters of storage (1, 2) , (2) , (3) , 15.04 square meters of building in the order of priority, (4) , (3) , 17, 17, 17, 17, 17, 4, 9, 14.
[Ground of recognition] Unsatisfy, entry of Gap evidence 1 to 3 (including branch numbers; hereinafter the same shall apply), the result of the appraisal commission to appraiser F by this court, the purport of the whole pleadings
2. Determination
A. The facts of the above recognition as to the cause of the claim.