(영문) 제주지방법원 2020.06.24 2019나12947
공사지연손해금
Text

1. Of the judgment of the court of first instance, the part against the defendant exceeding the following amount ordered to be paid shall be revoked.

Reasons

Facts of recognition

On October 19, 2016, the Plaintiff entered into a housing supply contract with the Defendant (hereinafter “each of the instant supply contracts”) with the content of the purchase of an urban residential housing E (hereinafter “E”) and F (hereinafter “F”) of the building D, non-resident-type, non-resident-type, and one parcel D (hereinafter “F”).

The parts relating to the instant supply contract relating to the instant case are as follows:

(A) Article 1 (Supply Amount and Payment Schedule) (1) "A" shall be supplied to the above indicated property and the corresponding amount shall be paid to the bank account in the name of "B" within the date specified in this Agreement.

The aggregate of the fixed-term installment payments of KRW 15,754,400, KRW 15,754,400, KRW 15,754,400, KRW 15,754,400, KRW 15,754,405, and KRW 15,754, and KRW 15,754,40, and KRW 15,754, and KRW 15,754,40, and KRW 15,754,40, and KRW 15,754,40, KRW 15,754,40, KRW 400, KRW 400, KRW 15,263,00, KRW 154,00, KRW 157, KRW 1540, KRW 405, KRW 157, KRW 4057, KRW 405, KRW 75,547, and KRW 405,

Provided, That where the planned construction schedule is considerably late than the payment schedule of the intermediate payment, "A" and "B" may adjust the payment schedule of the intermediate payment by agreement.

3.06% per annum of 5% per annum of 3.06% per annum of 3.06% per annum of 5% per annum of 3.06% per annum of 3 months or less of 3.06% per annum, but 3.06% per annum of 3 months or more.06% per annum.