logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 인천지방법원 2020.12.24 2019가단207201
공사대금
Text

The defendant's KRW 31,845,000 and its amount shall be 6% per annum from October 23, 2018 to December 24, 2020 to the plaintiff.

Reasons

. The “instant asbestos removal construction” refers to the “instant asbestos removal construction”

A. The name of the construction project: The construction site for the improvement of facilities inside and outside of the F unit building in 2018: the date of completion of the construction project: May 29, 2018: the contract price on December 14, 2018: the sale million won for the daily gold (80,000,000

6. Contract bond: None;

7. Advance: 40%;

8. A completed portion:

9. Settlement of the amount of completion: Within seven days after the completion of construction (100% in cash); 10. Warranty liability (in the case of a multi-functional construction work, classified by type of work) , the ratio of the contract amount for defect warranty (in the case of the multi-functional construction work), and the ratio of liquidated damages for defect warranty to 80,000,000 won for asbestos removal works: 1/100 of the total construction cost: 1/100 of the total construction cost; 100. Other matters

The contractor and the contractor shall enter into the contract by the contract document attached under the agreement of the contractor, promise to perform the contractual obligations in good faith, and shall prepare two copies of the contract document as evidence of this contract and keep one copy of each contract document.

*Annexed document: A project name of a contractor(A) contractor(B) of a written estimate: C representative: G representative: A

C. The Plaintiff received advance payment of KRW 35,200,000 (=88,000,000 x 40%) from the Defendant on the date of conclusion of the instant subcontract.

On August 2018, in order to determine the schedule of asbestos removal works in this case, the Corporation was found to have been unable to perform with respect to some areas of electric rooms, gas stations, etc. while confirming the site of the instant project. On September 3, 2018, the Plaintiff, the Defendant, and the E Corporation decided to remove (M-Bar) and re- install (hereinafter referred to as the “ removal works”) the light-weight steel framed mold, excluding the above part of the area from the asbestos removal works in the place where the Plaintiff, the Defendant, and the E Corporation are gathered on September 3, 2018.

E. On the basis that the Plaintiff was discussed on September 5, 2018 and September 6, 2018 at the above conference, the instant case is based on each changed quantity.

arrow