Text
1. The defendant shall pay 63.5 million won to the plaintiff and 12% per annum from March 21, 2020 to the day of complete payment.
Reasons
In light of the absence of dispute between the parties or the overall purport of evidence Nos. 3, 4, 6, and 8 and 12 (including paper numbers), and evidence Nos. 2 and 2 of the pleadings, the Plaintiff received a contract from the Defendant on June 26, 2019 by fixing the machinery and equipment construction work cost as KRW 379,500,000 (including value-added tax) from the Defendant on June 26, 2019. The Plaintiff agreed to change the construction cost into KRW 42,60,000 (including value-added tax) due to an increase in the scope of construction with the Defendant around November 2019. The Plaintiff completed the said construction and did not receive KRW 63,50,000 from the Defendant.
Therefore, the Defendant is obligated to pay to the Plaintiff the remainder of the construction cost of KRW 63.5 million and the damages for delay calculated by the rate of 12% per annum from March 21, 2020 to the day of full payment under the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, which is the day following the delivery date of the instant payment order, which