(영문) 서울남부지방법원 2017.04.20 2016가단259466
손해배상(기)
Text

1. The Defendants jointly share KRW 150,000,000 with respect to the Plaintiff and the Defendant Co., Ltd. from February 27, 2015.

Reasons

1. Indication of claims: It is as shown in the Attached Form “Cause of Claim”.

2. Judgment without holding any pleadings (Articles 208 (3) 1 and 257 of the Civil Procedure Act);

3. The dismissed portion (the Plaintiff claimed payment of damages for delay at the rate of 20% per annum from the day following the delivery of a copy of the complaint of this case to the day of full payment. However, the ground for claiming damages for delay at the rate of 20% cannot be known, and damages for delay under Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings can be sought. The statutory interest rate under the main sentence of Article 3(1) of the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings, which was wholly amended by Presidential Decree No. 26553, Sept. 25, 2015, was changed to 15% per annum from October 1, 2015 to 15).

arrow