logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 의정부지방법원 2016.07.08 2016가단8879
공사대금
Text

1. The Defendant shall pay to the Plaintiff KRW 27,100,000 and the interest rate of KRW 15% per annum from February 24, 2016 to the day of complete payment.

Reasons

1. Judgment on the plaintiff's claim

A. The facts subsequent to the facts of recognition may be acknowledged by integrating the purpose of the entire pleadings in each entry in Gap evidence Nos. 1, 2, and 3.

(1) The Plaintiff is a corporation with the purpose of conducting construction business, etc., and the Defendant is a corporation with each objective of building construction business.

(2) On April 1, 2015, the Plaintiff entered into a contract for a construction project to which the Defendant was awarded a contract by setting the construction cost of KRW 11,00,000,000, among the hotel works with the Defendant’s main hotel in the Defendant’s construction work.

(3) On August 4, 2015, the Plaintiff entered into a contract for construction with the Defendant, setting the construction cost of 40,000,000,000 won among the hotel-related hotel works in the future in the Defendant’s construction of the Defendant.

(4) Although the Plaintiff completed the above construction, it did not receive KRW 7,100,000,000 from the Defendant for the hotel construction cost, and KRW 20,000,000,000,000,000 out of the hotel construction cost in Boh-gu.

B. According to the above facts of recognition, the Defendant is obligated to pay to the Plaintiff delay damages calculated at the rate of 15% per annum from February 24, 2016 to the date of full payment, which is clear as the day after the original copy of the instant payment order was served on the Defendant (=7.1 million won) and the day after the original copy of the instant payment order was served on the Defendant.

2. In conclusion, the plaintiff's claim of this case is justified and it is so decided as per Disposition.

arrow