(영문) 서울서부지방법원 2015.07.16 2013가단51868
건물철거및토지인도등
Text

1. The defendant shall be the plaintiff.

(a) Attached sheet Nos. 3, 4, 5, 14, 15, 19, 20, 21, 21 on each land listed in the separate sheet;

Reasons

1. Basic facts

A. Each land listed in the separate sheet (hereinafter “instant land”) was originally owned by C and D, and the ownership of C was transferred to E on December 6, 2001, and the ownership of E and D was entirely transferred to F and G on December 21, 2006, while the ownership was entirely transferred to F and G on December 24, 201.

B. The land of this case was originally owned by JJ with H large 26 square meters and I large 261 square meters adjacent to the instant land. However, J constructed four-story housing on September 23, 1968, and the said four-story housing was transferred in sequence to K on March 9, 1990, to L on January 16, 1996, and to the Defendant on March 16, 2002.

C. Since August 16, 1982, there was a reinforced concrete retaining wall connecting each point of 10, 11, 12, 13, 14, and 15 as indicated in the separate sheet since the land of this case and H and I land, and there was red bricks.

On October 29, 191, one story of the above 4-story was extended to 35.10 square meters among them. On June 28, 2005, some extension was made. Of the above 4-storys, the appraisal of the attached Table 3, 4, 5, 14, 15, 19, 20, 21, and 3 shall also be marked, 14 square meters in the underground building section, 14 square meters in sequence, 2, 3, 21, 20, and 14 of the same map, 14 square meters in the ship, 2, 2, 3, 3, 20, 17 square meters in sequence, 16 square meters connected to each of the above 4-storys, 2, 3, 3, 21, 20, 16, 14, 15, 16, 16, 16, 16, 16, 14, and 14.

The above “A”.