1. The Defendant shall pay to the Plaintiff KRW 254,60,000 and interest rate of KRW 15% per annum from June 3, 2018 to the day of complete payment.

Reasons

1. Indication of claim;

A. On July 11, 2016 to February 28, 2017, the Plaintiff lent a total of KRW 250 million to the Defendant as follows.

Serial 1: 50,00,000 on July 11, 2016; 49,800,000 on July 11, 2016; 3.50,000,00 on August 28, 2016; 5,000,00 on August 15, 200 on August 16, 2016; 16,00,00 on August 16, 2016; 10,000,00 on October 4, 200, 200,007; 10,000,00 on August 30, 201, 200; 10,000,000 on July 30, 200, 2008; 10,000;

B. The Defendant is obligated to pay to the Plaintiff damages for delay calculated at the rate of 15% per annum from June 3, 2018 to the day of full payment, which is stipulated in the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings, from June 3, 2018, a copy of the instant complaint demanding the payment of the said KRW 254.6 million to the Defendant.

[Grounds for recognition] The entry of Gap evidence No. 2 and the purport of the whole argument

2. Article 208 (3) 3 of the Civil Procedure Act (Judgment by public notice).