(영문) 수원지방법원 2018.08.09 2018구합61568
도시계획시설사업실시계획변경인가신청반려처분 취소
Text

1. The instant lawsuit shall be dismissed.

2. The costs of lawsuit shall be borne by the Plaintiff.

Reasons

1. Basic facts

A. On September 19, 2012, a non-party 2 corporation (hereinafter “ non-party 2”) proposed the formulation of an urban management plan for KRW 727 Egypt-dong, Suwon-gu, Suwon-si, where a water-source cargo terminal was located, for the purpose of maintaining and improving infrastructure (road, green area) and publicly announcing the determination of an urban management plan (amended) for KRW 727 as well as the following conditions for the determination thereof (No. 2012-249).

Review of the adjustment of length of a lane or lane so as to meet the relevant standards;

(b) Infrastructure buffer greenbelts shall maintain the existing area as much as the area decreases;

(b) Acceptance of donations after completion of infrastructure;

(b).

On May 6, 2013, the Defendant publicly announced the designation of a project implementer and the authorization of an implementation plan (No. 2013-18, the public announcement in the Si of orchard), May 13, 2013, and the authorization of an implementation plan (No. 2013-129, the public announcement in the Si of orchard) with respect to the Suwon Urban Planning Facilities (No. 1-27 lines) on May 6, 2013. Accordingly, the project implementer of each of the above urban planning facilities (hereinafter referred to as the “instant project”) announced the implementation plan (No. 2013-129, the public announcement in the Si of orchard), respectively. The project implementer of each of the above urban planning facilities project (hereinafter referred to as “each of the instant projects”), who refers to both the urban planning facility project for the buffer green belt and the project completion date is no less than 7-12,000,0000 square meters and 728-27,000 square meters and 78-4,727.7.

C. On December 24, 2013, the vice versa divided the 728-4 square meters (203 square meters), 728-5 square meters (44 square meters), and 728-6 square meters (163 square meters) into the land of each of the instant projects, and completed green belt creation works and road construction works on the land of the instant project.