(영문) 전주지방법원 2017.06.22 2015나1225
건물명도
Text

1. A change in exchange between the Plaintiff (Counterclaim Defendant)’s primary principal claim and the trial that was added at the trial.

Reasons

A principal lawsuit and a counterclaim shall be deemed simultaneously.

1. Basic facts

A. On November 24, 2008, the Luxembourg Agricultural Cooperative completed the registration of creation of a neighboring building with the maximum debt amount of KRW 128 million and the debtor Q Q as the joint security of each building listed in the attached list Nos. 1 through 3 of the attached Table Nos. 3,221m2, M land for factory, M land for 1,418m2, P, L, and M as the joint security (hereinafter “each building listed in the attached list”).

B. D Co., Ltd. (hereinafter “D”) completed the registration of ownership transfer on January 20, 209 with respect to each building listed in the above land and the separate sheet on the same day.

C. The Defendant entered into a construction contract with D as to each building listed in the separate sheet, and completed the construction from May 20, 2009 to July 30, 2009.

Each building listed in the attached list due to construction has been changed in the size, structure, etc. as follows:

(1) After completion of construction on each building listed in the separate sheet, each of the buildings described in the separate sheet, with the following: “A”, “this case’s (B), “A”, and “D”). After the completion of construction on the attached sheet, the current status (based on appraisal standard) of the construction on the transfer of the attached sheet, P from North Jeju-gun, North Jeju-gun P or M1 to the land (based on appraisal) before and after the completion of the construction on the attached sheet, and the current status (based on appraisal) of the attached sheet, 95.04m2, 95.04m2, 95.04m2, 95.04m2, and 97m2,0000,00000,00000,0000,0000,000,0000,000,0000,000,0000,000,000,000,000.

D. On August 30, 2009, the Plaintiff settled additional materials costs, personnel expenses, etc. with D and the total construction cost is KRW 24,4520,000.