(영문) 의정부지방법원 2019.04.03 2018가단19408
공사대금
Text

1. The Defendant’s KRW 73,255,00 and KRW 66,595,45 among the Plaintiff’s KRW 73,255,00 per annum from September 17, 2017 to September 10, 2018.

Reasons

1. The assertion and judgment

A. The main point of the parties’ assertion is that the Plaintiff received a subcontract from the Defendant and completed the steel framed construction, and only some of the construction cost was paid, thus seeking the payment of the unpaid construction cost.

As to this, the defendant did not receive a subcontract from the defendant as to the above steel framed, and it is not a subcontract from the defendant as to the above steel framed, and as the plaintiff was aware of the fact that the defendant lent the business name to C, it is not possible to accept the plaintiff's claim in the end.

B. 1) Determination of the cause of the claim is based on the introduction of C, which is the director at the site of the Defendant’s affiliation, as follows. The Plaintiff entered into a subcontract with the Plaintiff and the Defendant as follows. The Plaintiff’s 231 million won (including value added tax; hereinafter the same shall apply) from the Defendant among the new construction works of the steel company located in Gangwon-gun D, Gangwon-gun.

(2) Upon receipt of a subcontract from the Defendant, the said construction work was completed on or around May 4, 2017. The Plaintiff completed the said construction work on or around May 12, 2017 with a subcontract of KRW 183,70,000 among the new construction works in Gangwon-gun E located in Gangwon-gun; the Plaintiff received a subcontract of KRW 198,000,000 from the Defendant for the steel-frame construction works located in Gangwon-gun, and completed the said construction work on or around June 19, 2017; the Plaintiff received a subcontract of KRW 65,00,000 from the Defendant for the said construction works; the Plaintiff completed the said construction work on or around September 16, 2017; the price for supply of the steel-frame for three hundred and five hundred five hundred and five hundred and five hundred and five hundred and five hundred and five hundred and five hundred and five hundred and five hundred and five hundred and five hundred and five and five hundred and five hundred and five hundred and five hundred and five hundred and five hundred and five and one and one hundred and five hundred and one and five hundred and one and one of the parties’s of the above construction price.