1. The defendant,
A. The Plaintiff KRW 129,842,576 as well as 5% per annum from September 30, 2013 to August 29, 2018.
Reasons
1. Basic facts
A. The relationship between the parties 1) The Defendant is a company that manufactures metal products, such as road drails, safety launch plates at construction sites, and hack pipes columns. 2) The Plaintiff entered into an employment contract with the Defendant on July 19, 2013, and has been put into the manufacturing process of safety launch plates or hack pipes around that time.
B. 1) Safety project machinery installed in the Defendant’s Cdong factory is designed to be carried out by the process of fixing a day (raw board). ① The process from which the framework is stamped, ③ the mincing machine process (the process in which the mincing machine moves between rollers) and ④ the process of mincing machines, etc. ④ When the work is to move from 17 rollers to 18 rollers, the work is to stop the operation of the machinery by the mincing machine and then put the 3rd part of the mulcing machine into the 5th amper’s upper end (c) and then stop the operation of the machinery by using the 17 amper and the 18 amper, and then stop the operation of the machine and then stop the operation of the machine by using the 10 amper’s 3rder.