Text
1. The defendant shall pay 64,233,400 won to the plaintiff and 12% per annum from March 10, 2020 to the day of complete payment.
Reasons
1. Determination as to the cause of claim
A. According to the evidence evidence Nos. 1 through 3, there is no dispute between the parties, or the defendant, who was awarded a contract for E-Newly constructed (civil engineering and construction) by the non-party D Co., Ltd., subcontracted the construction of landscaping facilities to the plaintiff among the above new construction works on November 26, 2019, and even though the plaintiff completed the construction of the above landscaping facilities, the defendant paid only KRW 19,900,00 out of the construction cost of KRW 184,13,400.
B. According to the above facts, the Defendant is obligated to pay the Plaintiff the amount of 64,233,400 won unpaid (=184,133,400 won - 119,900,000 won) and the damages for delay calculated at the rate of 12% per annum under the Act on Special Cases Concerning Expedition, etc. of Legal Proceedings from March 10, 2020 to the date of full payment, which is the day following the delivery of a copy of the complaint of this case.
2. In conclusion, the plaintiff's claim of this case is justified and it is so decided as per Disposition.