logobeta
본 영문본은 리걸엔진의 AI 번역 엔진으로 번역되었습니다. 수정이 필요한 부분이 있는 경우 피드백 부탁드립니다.
텍스트 조절
arrow
arrow
(영문) 수원지방법원 안양지원 2012.08.07 2011고단1463
사기
Text

A defendant shall be punished by imprisonment for not more than ten months.

Reasons

Punishment of the crime

1. Around April 29, 2010, the Defendant entered into a contract with C and “A” to purchase a parcel of land outside of 1.056 million won during the period of Ansan-si owned by C, and immediately pay the down payment and the intermediate payment of KRW 600 million, and the remainder was newly constructed eight households on the land and paid as two households.

around August 4, 2010, the Defendant contracted F with F for the remainder of the structural frame (civil engineering), electricity, facilities, external decorations, interior works, etc., except for the foundation (civil engineering) construction, and F subcontracted the said construction to G, while G subcontracted the interior and external works, including building stones construction, to H.

However, the remainder of the construction work that must be carried out may be conducted, but the Defendant urged G to proceed with the building work, and accordingly, G to pay KRW 85 million for the construction cost on February 2, 201, and the victim I had the victim I proceed with the building work.

However, in order to carry out a stone construction work, the victim could not have the victim do the construction work on the ground that H was awarded a subcontract for the stone construction work. Accordingly, the victim suspended the construction work without the owner's security.

2. On February 9, 2011, the Defendant stated that “The Defendant would give the victim a contract for sales in lots (No. 302) with the view to preserving the construction cost of stone construction without molding the construction cost and securing the payment of the construction cost. The Defendant paid the construction cost of KRW 85 million within 40 days after the completion of construction, and the contract for sales in lots shall be returned, and if the construction cost is paid, the contract will be returned, and if the construction cost is not paid, 302 shall be ordered.”

However, the defendant does not have any funds to construct E-B lending from J and K.

arrow