(영문) 춘천지방법원강릉지원 2019.04.30 2018가합30804
추심금
Text

1. The Defendant’s KRW 66,100,000 as well as 5% per annum from October 17, 2018 to April 30, 2019 to the Plaintiff.

Reasons

1. Facts of recognition;

A. C Co., Ltd. (hereinafter “C”) 1) Co., Ltd. (hereinafter “C”).

(2) On February 25, 2016, the Defendant removed from the Defendant’s new hotel construction works (hereinafter “instant 1 corporation”).

(i) contract amount of KRW 1,849,800,000 (including value-added tax; hereinafter the same shall apply)

(2) From February 25, 2016 to May 5, 2016, C and the Defendant concluded a contract to alter the terms of “the contract amount of KRW 2,090,000,000, and the period of construction from February 25, 2016 to August 31, 2016.” C and the Defendant maintained the contract amount under the aforementioned paragraph (2) from January 31, 2017 to May 5, 2016; and (b) concluded a contract to change the terms of “the construction period from February 25, 2016 to August 30, 2018.”

(C) The Plaintiff was awarded a contract by designating the contract amount of KRW 605,00,00 and the period of construction from February 12, 2018 to May 31, 2018. Each of the instant seizure and collection orders 1) based on the executory exemplification of the judgment in relation to C’s claim for service payment amount of KRW 2016,50,50866, the Plaintiff received a seizure and collection order (hereinafter “instant seizure and collection order”) from the Defendant, who was the debtor, on July 5, 2018, with the same court 2018, 279,822,380, out of the first construction cost claim against C against the Defendant. The instant seizure and collection order was served on the Defendant, who was the debtor on July 3, 2018.

2) Based on the executory exemplification of the judgment regarding the claim for service payment against C, the Plaintiff’s order of seizure and collection (hereinafter “instant order”) as to KRW 286,486,638 out of the claim for the second construction payment against C, the same court No. 2018TT21860, Sept. 5, 2018, as to KRW 286,486,638 among the claim for the second construction payment against C.