Text
1. The defendant,
A. From August 13, 2014 to Plaintiff (Appointed) KRW 13,552,234 and its related thereto:
(b) the selector;
Reasons
1. The Plaintiff (Appointed Party) and the designated parties to the claim shall be employed by the Defendant and work as indicated in the Verification Board (Evidence A) for the unpaid money and valuables.
The retirement was withdrawn.
However, the defendant does not pay each of the wages specified in the order to the plaintiff (appointed party) and the appointed party without an extension of the due date.
Therefore, the defendant is obligated to pay to the plaintiff (appointed party) and the appointed party the amount corresponding to the order and damages for delay at the rate of 20% per annum from the day following the 14th day from the date of retirement to the day of complete payment.
2. Article 208 (3) 1 of the Civil Procedure Act of the applicable provisions of Acts.