(영문) 서울중앙지방법원 2014.06.26 2013가단265778
공사대금
Text

1. The defendant shall pay 38,400,000 won to the plaintiff and 20% per annum from October 25, 2013 to the day of complete payment.

Reasons

1. Facts of recognition;

A. The Plaintiff is a company with the objective of maintaining and managing facilities, conducting structural safety diagnosis, and the Defendant is a company with the objective of general construction business, housing construction business, and housing site creation business, etc.

B. On February 4, 2013, the Plaintiff paid sewage by setting the construction cost of KRW 64,00,000 (excluding value-added tax) and the construction period from March 11, 2013 to April 11, 2013.

C. The Plaintiff completed the instant construction within the said construction period, and received payment of KRW 32,00,00 in total of KRW 6,400,000 on February 25, 2013, and KRW 12,80,000 on March 13, 2013, and KRW 32,800,000 on April 2, 2013 (i.e., KRW 6,400,000 in total of KRW 12,80,800,000) from the Plaintiff as the construction price.

[Reasons for Recognition] Unsatisfy, Gap evidence Nos. 1, 2, 3, and 6 (including virtual numbers), the purport of the whole pleadings

2. Determination as to the cause of claim

A. According to the above facts, barring any special circumstance, the Defendant is obligated to pay the Plaintiff the remainder of the construction cost of KRW 38,400,000 (i.e., value-added 6,400,000, value-added 6,400,000 - 32,000,000) and damages for delay.

나. 피고의 주장에 관한 판단 ⑴ 미시공 공사대금 공제 주장 ㈎ 피고는, 원고가 이 사건 공사 중 1층 기초 부분 보강공사, 계단실 기둥 2개 RC 보강공사와 4층 보 2개 RC 보강공사를 하지 않아 피고가 직접 15,694,000원의 비용을 들여 공사 마무리를 하였으므로, 위 금액은 피고가 지급하여야 할 공사대금에서 공제하여야 한다고 주장한다.

㈏ 살피건대, 을 제1, 2, 3호증의 각 기재만으로는 피고가 주장하는 위 미시공 공사 부분이 원고와 피고 사이의 이 사건 공사계약에 따른 공사 범위에 속한다고 인정하기에 부족하고, 달리 이를 인정할 만한 증거가 없다.

Therefore, this part of the defendant's argument is added.