(영문) 서울남부지방법원 2009.06.11 2008가합26019
연대보증금 및 양수금
Text

The defendant's KRW 150,062,961 and KRW 87,062,961 among them shall be 5% per annum from July 1, 2004 to January 8, 2009.

Reasons

1. Indication of claim;

A. Claim for damages for delay calculated according to the interest rate under the Civil Act and the Act on Special Cases Concerning the Promotion, etc. of Legal Proceedings from July 1, 2004, which is the day following the closure of C, for the Defendant, the joint and several surety of the Plaintiff, and for the newspaper site supplied by the Plaintiff under a newspaper site supply contract with Nonparty C from October 1, 2002 to August 1, 2002, for the amount of KRW 87,062,961, and for the amount of damages for delay calculated in accordance with each of the interest rates

B. Of the loans equivalent to KRW 80,000,000 against the Defendant of Nonparty D, the remainder of KRW 63,000,000 which was paid by the Defendant deducted the remainder of KRW 17,000,000 paid from the Defendant, and the Plaintiff’s claim against the Defendant for the amount of KRW 63,000,000,000 which was paid by the Defendant and damages for delay

2. Judgment without holding any pleadings (Articles 257 (1) and 208 (3) 1 of the Civil Procedure Act);