(영문) 수원지방법원여주지원 2020.07.23 2019가단1666
건물철거 및 토지인도등
Text

1. The Defendant shall enter the Plaintiff (Appointed Party) and the Appointed C in the annexed list on the ground of 694 square meters of forests and fields in Gyeonggi-do.

Reasons

1. Determination as to the cause of claim

A. 1) The fact of recognition is 694 square meters of forests and fields D (hereinafter “instant land”).

As to September 17, 2010, the transfer registration under the name of E was completed; the transfer registration under the name of F was completed on June 18, 2012; the transfer registration under the name of G was completed on December 3, 2013; and the transfer registration under the name of the Defendant was completed on March 26, 2015. With respect to the instant land, the maximum amount of debt on June 18, 2012; the establishment registration under the name of H association with the debtor F was completed on June 19, 201; the transfer registration under the name of H association with the debtor F was completed on June 31, 200; and the transfer registration was completed on June 29, 2012 under the name of the debtor F; and the transfer registration was completed on June 29, 2017 to the Plaintiff 3rd 1, 2015 (the Plaintiff’s voluntary decision to commence the auction procedure was completed on June 29, 2017.

3) On the instant land, the buildings listed in the separate sheet (hereinafter “instant building”) are as follows.

4) On October 22, 2012, F entered into a contract for the instant building to be newly constructed on the instant land with the building owner, and subsequently, had the building owner carry out the instant construction. On December 3, 2013, G sold the instant land and the instant building under construction. At the time of sale, at the time of the sale, the instant building had the shape and structure of the independent building under social norms as well as the columns, roof, main walls, and the exterior of the building.

5 The defendant shall simultaneously submit the instant land and the instant building from G on March 26, 2015.

arrow