(영문) 서울중앙지방법원 2015.08.27 2014가합37892
전시장치공사대금등
Text

1. The Defendant’s KRW 25,884,232 as well as the Plaintiff’s KRW 6% per annum from May 26, 2014 to August 27, 2015.

Reasons

Basic Facts

The plaintiff is a company that engages in the business of supplying and installing exhibition devices, and the defendant is a company that supervises the fair, etc.

On May 7, 2013, the Defendant concluded a contract with the Plaintiff for the integrated display equipment construction work (hereinafter “instant contract”) and contracted the Plaintiff for the installation work of the display equipment (hereinafter “instant construction”).

The service standard contract concerning the contract of this case (hereinafter referred to as the "contract of this case") contains the following contents, attached thereto, and the specifications concerning the substitute exhibition such as the attached document (hereinafter referred to as the "statement of this case") and the small exhibition are attached. ① The description of this case is 1. Basic Schedule-A type;

2. Basic Part (B) -B;

3. The chief of the consultation group;

4. Roster devices;

5.The stage of cargo entry and exit;

6.As classified into "other works", each description includes the size, unit, quantity, unit price, and amount, and the end is written to the effect that the total amount is KRW 33,00,000,000, including value added tax, and ② The description of the small exhibition is 1. Trast system;

2. Personnel expenses,

3.Electric construction (Campt);

4.Neline Line Works;

5. Construction works with the entrance partitions of the second floor;

6.Transport costs;

7. Each name is divided into "public expense" and written to the effect that the size, unit, quantity, unit price, and amount are written, and that at the end, the total amount is KRW 4,500,000, including value-added tax.

Standard contract terms - Contract Terms and Conditions - Contract Terms and Conditions - Contract Terms and Conditions : Integrated Exhibition System: Contract Amount: unit price for each event including V.A.T. - Contract Terms and Conditions - From May 7, 2013 to December 31, 2014 ( changed according to the schedule of the event) - Other matters according to the schedule of the event site: The plaintiff and the defendant.