(영문) 서울서부지방법원 2020.07.24 2020가단244323
대여금
Text

1. As to KRW 51,284,667 and KRW 40,000 among them, the Defendant shall annually pay to the Plaintiff KRW 51,284,667 from February 1, 2017 to April 21, 2020.

Reasons

1. At the request of the Defendant, the Plaintiff received credit loans and secured loans from the Defendant, and KRW 15,00,000 on July 28, 2010;

8.6. 25,00,000 won each loan, and 8.4% interest per annum on the above loan was agreed to be repaid by the Defendant, and the Defendant’s repayment of only KRW 18,972,00 among the interest accrued until January 2017 may not be disputed between the parties, or may be acknowledged by comprehensively taking into account the purport of the entire pleadings in each statement in subparagraphs A through 3.

2. According to the above facts of recognition, the defendant is obligated to pay to the plaintiff damages for delay calculated at the rate of 51,284,667 won (40,00,000 won 30,256,667 won - 18,972,00 won) and 40,000 won from February 1, 2017 until April 21, 2020, which is the delivery date of the original copy of the payment order of this case, 8.4% per annum and 12% per annum from the next day to the day of complete payment.

3. The plaintiff's claim is accepted.