(영문) 인천지방법원 2015.01.14 2014가합52168
사해행위취소
Text

1. Defendant A, B, and C jointly and severally with the Plaintiff KRW 1,208,480,602 and KRW 596,568,095 among them.

Reasons

1. Guarantee principal ( modified amount) guaranteed principal of a financial institution (amended amount) at the time limit on November 27, 2002, the Industrial Bank of Korea 85,000,000 won (64,000,000 won) at the time limit on November 26, 2003 ( November 14, 2014) shall be KRW 400,000,000 in our bank on May 7, 2009 ( April 18, 2014) and KRW 600,000,000 in the Republic of Korea on May 6, 2010 ( April 18, 2014) at the time limit on April 19, 2013.

The Plaintiff entered into a credit guarantee agreement with Defendant A Co., Ltd. (hereinafter “Defendant Company”), which covers the repayment of the principal and interest of loans from each financial institution, and issued each credit guarantee agreement with each financial institution as follows, and Defendant B and C jointly guaranteed their respective obligations to the Plaintiff at the time of the above credit guarantee agreement.

B. On November 27, 2002, the Defendant Company offered a loan of USD 100,000 from the Industrial Bank of Korea as security for the first credit guarantee agreement; KRW 500,000,000 from the Bank as security for the second credit guarantee agreement on May 8, 2009; KRW 750,000,000 from the New Bank as security for the third credit guarantee agreement on April 20, 203; and USD 480,000 from the Bank as security for the third credit guarantee agreement on April 23, 2013; but each of the above financial institutions lost its interest for each of the above loans due to a credit guarantee accident on December 3, 2013; and each of the above financial institutions claimed against the Plaintiff for the performance of guaranteed obligations under the first or fourth credit guarantee agreement.

C. Accordingly, on December 23, 2013, the Plaintiff, among the principal and interest of loans in arrears of the Defendant Company, 64,359,676 won (i.e., the principal amount of 64,00,000 won and interest of 359,676 won) due to a credit guarantee agreement with the Industrial Bank of Korea on December 23, 2013 (i.e., the principal amount of 64,00,000 won and interest of 359,676 won), and on December 18, 2013, 402,409,997 won and interest of 399,80,192 won and interest of 2,609,805 won and interest of 399,805 won) due to a credit guarantee agreement with Korea