Text
1. The defendant shall pay 640,000,000 won to the plaintiff and 20% per annum from August 8, 2014 to the day of complete payment.
Reasons
1. Basic facts
A. The defendant related to the parties is a company with the main purpose of the construction business and the housing construction business, and its representative director C is punished D, and D is between D and D, known to the plaintiff.
B. 1) On June 26, 2013, the Plaintiff was not able to perform the duty of care as stipulated in the following sub-paragraph (hereinafter “instant sub-paragraph (1)” between D and D.
2) The Defendant’s seal impression is affixed to the column (a) adjacent to the entry of “B representative director C” at the bottom of the instant landmark, and D’s seal impression is affixed to the column (a) adjacent to the entry of “President D.”
(W) Creditor: D (F) debtor's office at Chang-si, Chang-si: D (F) debtor's office at Chang-si: The debt amount (f) H 201 in Chang-si, Chang-si: The debt amount (f40,000,000): Geum-si, Chang-si: The debt amount (f40,000: 50,000,000) at September 29, 2006: The debt amount at KRW 10,000 (10,000,000,000) at KRW 7, 2006: May 2008, 200 to May 2009; the debt amount at KRW 40,000 (40,000,000) at KRW 10,000,000,0000,0000 and the debt amount at KRW 320,000,000,0000) at each of the above creditors.
In addition, the second installment construction is being made up of the second installment construction. A debtor (the second installment) shall establish a bank for the settlement of accounts, and I shall establish a new corporation, and shall establish and complete K 16 households with investments from the KJ and the KJ on the fourth installment. The second installment construction shall be made up of the second installment construction. The first installment payment shall be made between the bank for the settlement of accounts and the KMB, and the KMB, which shall be entrusted to A, and the second installment (gains) shall be made between the bank for the settlement of accounts, and shall not be made simultaneously with the second installment construction contract: not less than 50 percent of the K profit, but not more than 45 days (not less than 30 million won): The debt balance (not less than 340 million won): the balance of the second installment construction (which shall be settled in full) and the amount of the second installment (which shall be settled in full).