(영문) 전주지방법원 2016.01.21 2014나7585
토지인도 등
Text

1. The plaintiff's appeal against the defendants is dismissed in entirety.

2. The costs of appeal shall be borne by the Plaintiff.

purport, purport, and.

Reasons

1. The following facts can be acknowledged in full view of the following facts: Gap's facts do not conflict between the parties, or Gap's statements, 12, 13, 18 through 20, 41, 55 through 75, Eul's statements, and Eul's statements, 13 (including additional numbers), and the whole purport of the arguments in the first instance court's fact inquiry with regard to the head of the Jinan-gun of the court of first instance.

The land division was conducted as shown in the annexed Form No. 4, while the land category was changed or the lot number was subject to registration conversion in the process of the land division as shown in the annexed Form No. 39,978 square meters in Jinan-gun, Jeollabuk-do (hereinafter “J land before subdivision”), L farm site 19,835 square meters (hereinafter “land before subdivision”), M forest land M 7,835 square meters (hereinafter “M before subdivision”) and N or O forest land (hereinafter “ri”).

B. The instant land divided on November 26, 2001 from L before subdivision was owned by E, and the Plaintiff completed the registration of ownership transfer in the Plaintiff’s name as to the instant land on March 10, 208.

C. As of August 10, 200, Defendant B, the representative director of FF farming association, filed an application for a building permit with the competent authority to construct a stable on land, the lot number and land category of which are 1,054 square meters in G stock farm site, 5,900 square meters in H stock farm site (O is subject to registration conversion), 19,196 square meters in I stock farm site (P is subject to registration conversion), and the construction permission was commenced on September 9, 200 and was approved for use on January 31, 202 for livestock shed.

In order to construct the above stable around September 200 and enter the land for the said stable as a contribution, Defendant B contained cement packaging on the land for the instant mountain dispute, which is part of the land indicated in attached Table 1, “B” and “D,” and thereafter, the land for the instant mountain dispute is used as a passage to enter the said stable as a contribution.

E. Defendant Company G and H.

arrow